Leh: As per Ministry of Home Affairs Annual Report on Ladakh, there has been a major improvement in reliable power supply in Ladakh following commissioning and strengthening of 220 KV Srinagar-Leh transmission line.
JOIN OUR WHATSAPP GROUP FOR REGULAR NEWS UPDATES FROM LADAKH
The report also said that five DG sets have been phased out by providing Grid connectivity during 2021-22 as a step towards carbon-neutral Ladakh.
“Work on 220 KV transmission line from Phyang to Diskit, Nubra and Drass to Padum, Zanskar has been started with a project cost of Rs 1309.72 crore. With completion of the transmission line, Nubra and Zanskar will get 24×7 power supply through the Grid,” the MHA report said.
It added that a 50 MW Solar Power Project at Taru, Leh approved under Prime Minister’s Development Plan (PMDP), has been taken up by the SECI for execution and completion of project will reduce load on 220 KV Srinagar-Leh transmission line during winter and also during peak demand.
The Transport Department of Ladakh has also taken steps towards carbon-neutral Ladakh by procuring 10 electric buses for public transport, of which, two are already in operation in Ladakh. In addition, the Transport Department is also procuring 10 electric cars inclusive of solar charging car port during current financial year for use in the Government, as per the report.