Leh, October 28: Chief Secretary Ashish Kundra on Wednesday reviewed Ladakh’s power sector, directing departments and agencies to accelerate project execution, strengthen transmission infrastructure and improve coordination to ensure reliable electricity supply across the Union Territory.
Chairing a review meeting of the Ladakh Power Development Department (LPDD), Kundra assessed the progress of power generation, transmission and distribution projects, renewable energy initiatives and measures to address seasonal variations in electricity demand and availability.
The meeting reviewed ongoing and proposed hydropower projects, including Takmachik and Nimoo-Basgo, along with other power generation initiatives. Kundra stressed the need to expedite the preparation of Detailed Project Reports (DPRs), set clear implementation timelines and strengthen project monitoring to ensure timely execution and effective utilisation of Ladakh’s power generation potential.
He also reviewed the institutional framework governing the sector, including the roles of the Power Development Department (PDD), Power Development Corporation (PDC), Ladakh Renewable Energy Development Agency (LREDA) and Kargil Renewable Energy Development Agency (KREDA). He emphasised clearly defined responsibilities, appropriate staffing structures and accountability mechanisms to improve coordination and implementation.
Transmission capacity and power evacuation infrastructure featured prominently in the discussions. The meeting examined hydropower development in Zanskar, transmission works at Phey and Zanskar, and the evacuation of electricity from projects in Dha and Hanu. Kundra stressed that generation capacity must be matched by adequate transmission infrastructure to prevent underutilisation of available power.
To strengthen year-round energy security, he called for a comprehensive assessment of electricity demand and availability during summer and winter, taking into account seasonal hydropower generation, solar power availability, electricity purchases from external sources, power purchase agreements and their financial implications.
The proposed establishment of a State Load Despatch Centre (SLDC) was also discussed, including the identification of a suitable location, institutional arrangements and the availability of qualified technical personnel. The proposed centre is intended to strengthen grid management, improve coordination and optimise power flows.
Reviewing projects under the Revamped Distribution Sector Scheme (RDSS), Kundra sought updates on the Leh, Kargil and Changthang packages, as well as transmission connectivity in Nubra, Turtuk and Zanskar. He called for close monitoring of physical progress, contractor performance and implementation timelines, with delays to be addressed to ensure completion within the stipulated schedules.
The meeting also examined pending transmission towers and the proposed Nubra–Khardung La transmission line.
Progress under the PM Surya Ghar: Muft Bijli Yojana was reviewed, with discussions covering rooftop solar installations, vendor selection, subsidy disbursement, inspections and online monitoring. Kundra called for transparent procedures, timely processing of eligible subsidy claims and effective use of digital platforms to track implementation. Renewable energy projects in Zanskar, along with metering and execution-related issues, were also discussed.
The Chief Secretary directed the concerned departments and agencies to establish clear project-wise responsibilities and undertake regular reviews of implementation. He emphasised integrated planning of generation, transmission and distribution infrastructure to strengthen energy security, improve resource utilisation and ensure reliable electricity supply to consumers across Ladakh.
The meeting was attended by Secretary, Power Development Department, Himanshu Gupta; Superintending Engineer Tundup Spalzang; Officer on Special Duty to the Chief Secretary for Special Projects Moses Kunzang; Executive Engineer Anwar Hussain; members of RDCL and other concerned officers.